Custom Concrete Skatepark Construction Outline – In-Kind Donations

 

I. Preconstruction

1. Location of underground utilities Survey of Site

2. Surveying of site for initial grade and drainage work

3. Geotech report

 

II. Demolition and Earthwork

1. Bobcat or skid steer loader

2. Excavation equipment – Large/Medium/and Small

3. Roller compactor

4. Dozer or grading equipment

5. Good fill for import

 

III. Drainage

1. Surveyor

2. Piping and drain lines

4. Sewer connections

5. Excavation equipment

 

IV. Rough Excavation and Coping Placement

1. Surveyor

2. Rebar (#5 – 30-50 units)

3. Schedule 40 Black Steel Pipe - `129 lin ft. various rolls, etc.

4. Concrete (small quantity – 8-10 cubic yards) – any mix

 

VII. Cast in Place Work

1. Surveyor

2. Rebar (#4 – 300-400 20’ units) -

3. Wood (2x4’s – 120 16’ spruce, ¾” plywood – 20 sheets CDX, masonite –

30 sheets)

4. Concrete

 

V. Shotcrete Work

1. 185 cfm diesel trailer air compressor

2. Mini-Excavator

3. #3 Rebar (600 20’ units)

4. Wood (2x4’s – 120 16’ spruce, ¾” Plywood 40 sheets, masonite – 10 sheets,

1x10 spine/spruce – 200 lin. ft., wooden landscaping stakes 12” and 18”)

5. Concrete


VI. Flatwork

1. #3 Rebar – 200 20’units

2. Wire Mesh – 50 5’ x 10’ units

3. Wood (2x4’s – 20 16’ pieces, masonite – 5 sheets)

4. Concrete

5. Boom type concrete pump

 

VII. Miscellaneous

1. Bobcat or skid steer – every day

2. Lodging for 8 adults

3. Stick Welding Equipment – preferably generator Welder (Bobcat 250)

4. Ground Level Storage Container (2 – 20’ or one 40’)

5. No Trespassing Signs

6. Orange Safety Fencing

7. Tree Protection/Silt Fencing

8. Generator if no power available on site

9. Vibratory Plate Compactor

10. Trailer Concrete Pump

11. Metal Pin Stakes 12, 18, and 24” (3 dozen each)